It's what dreams are made of and nightmares kindled: Most home owners aspire to it; some take a few tentative steps and fewer still are crazy enough to go the full hog! This blog shares some of the trials and tribulations of a major redevelopment of a 1950s home through a cataclysmic transformation which retains the best of the last Century while metamorposing the property into a design classic fit for today's living.

Tuesday, February 20, 2007

WEEK 47 - It's uphill from here (Delay = 31 weeks)

Whether it's global warming or something in the water, the silly season has arrived early.

As part of the concluding stages of the project, we've presented the contractor with a list of issues to resolve, or snagging, which should enable the crew to complete the project in a reasonable manner and standard. The starting point for this process was the most recent site meeting.

Having waited patiently for the last week and a half, it was time again to prod the contract in the hope they may come up with the much promised "programme of works". The programme is proving elusive and as we've ever only had one during the whole project - still showing 16 weeks as the target completion. It is little wonder the next update remains outstanding.

In the meantime, they've found a series of issues which require further AIs (architect's instructions), which more often than not means additional costs. Now, if we ask someone to do something over and above what was originally billed, asking for an AI is perfectly legit. However, if we're asking the guys to finish what they've already started, why do they need an AI for items such as manholes for drains (no manhole=no legal drain), filling holes from old pipes, reinstating load-bearing cills wrongly removed, fitting suitable locks suitable for doorhandles etc etc?

While eagerly awaiting the avalanche of AIs, the contractor has made it clear they're unable to programme the works and, therefore, return to site. It's nuts and the project could be heading for Phase 2 very shortly!